No current asbestos register
All asbestos likely to be disturbed must be identified and, so far as reasonably practicable, removed before demolition. With no current register, every area had to be identified from scratch.
Burke Industries demolished Toowoomba's High Street Plaza ahead of its redevelopment. We identified and removed asbestos without a register, recycled over 85% of all material and returned about 8,000 tonnes of crushed concrete to the site. Our asbestos, demolition and earthmoving teams delivered the job together, on time and on budget.

High Street Plaza was being redeveloped into a new shopping centre, and the old plaza had to come down first.
All asbestos likely to be disturbed must be identified and, so far as reasonably practicable, removed before demolition. With no current register, every area had to be identified from scratch.
Asbestos floor tiles from previous buildings were buried on the site, so they had to be dealt with as demolition uncovered them.
Landfilling the centre's concrete would have added transport, gate fees and the Queensland waste levy.
The job was a combined effort across Burke Industries' divisions, so the client dealt with one contractor from asbestos identification through to civil works.
We worked directly with the client to identify every area of asbestos before demolition, and dealt with the buried floor tiles as demolition progressed.
We demolished the plaza and recycled over 85% of all material off-site. Concrete was crushed at our Toowoomba facility, and about 8,000 tonnes came back to the site for reuse.
Our earthmoving division carried out the detailed earthworks and civil works, and supplied machine hire to most other subcontractors on site.
We re-directed stormwater and installed services for the new centre, working with the project engineers and hydraulic consultants.
Recycled concrete attracts no Queensland waste levy, and crushed concrete returned to site is material the new development did not have to bring in.

Tell us about the site, any asbestos register or survey, and your timeline. We'll plan the asbestos removal, demolition, recycling and civil works as one program.